How to perfect and enforce your Illinois Mechanics Lien Claim on private projects

featured image

This is our third installment in our series on Illinois Mechanics Liens. Now that we have looked at what a lien claim is, the parties entitled to file a lien claim and what is required to entitled to file a lien claim, we will now look at the steps that need to be taken in order to perfect and enforce a lien claim against a private project.

‘Perfecting’ your Illinois Mechanics Lien Claim

General Contractor’s Claim for Lien

Perfection is the process of converting a general lien right into an enforceable and valuable right in the real estate. This is done by a written document called a claim for lien. It is important that the contractor first obtain a title report or search public records to determine the legal description, the owner of record and whether any other parties have an interest in the property at issue. Once you have reviewed the the title work, you must now draft the claim.

A General Contractor’s claim for mechanics lien must be contain:

  1. A brief statement of the contract and the work performed;
  2. Date the work was completed;
  3. The balance due after all payments and credits; and
  4. A sufficiently correct description of the property and a PIN if available
  5. Names of the owner(s) of record, the party the contractor contracted with, and any mortgagees or lenders

A claim for lien must be verified (i.e. signed in front of a notary) and be recorded within four (4) months of the last date of work or furnishing at the project. The lien claim is recorded in the office of the country recorder where the real estate lies.

Additionally if a general contractor is preparing a lien claim against an owner occupied residence, it must serve a recorded copy of the lien to the owner within 10 days of recording.

Once a general contractor records the lien claim it can be enforced.

Subcontractor Notices and Lien Claim

In order for a subcontractor to enforce its lien claim, it must also prepare the same mechanics lien claim as a general contractor but it also needs to identify all parties in the chain of contract between the subcontractor and the owner which includes the general contractor and any other subcontractors in between.

Section 24 Notice

In addition to recording a lien claim, subcontractors also have notice requirements that must be followed. A subcontractor is required to serve a Notice of Claim to the owner within 90 days if its last date of work or furnishing pursuant to Section 24 of the Illinois Mechanics Lien Act.

The Notice of Claim must

The requirements of the Subcontractor’s Notice of Claim are very similar to those of the claim for lien and can be the same document. The notice must be served via certified mail with return receipt requested or served personally. If the notice is not timely served, the subcontractor will lose its lien rights.

There is an exception to the notice requirement. A notice might not be required in instances when the General Contractor has tendered a sworn statement pursuant to Section 5 of the Illinois Mechanics Lien Act which identifies the subcontractor, its contract amount and balance due. The sworn statement can provide sufficient notice to the owner of the subcontractor’s claim. However, it is often difficult to determine whether or not this has happened especially if the relationship between the general contractor and the subcontractor has deteriorated. It is always best to serve the Notice of Claim within 90 days.

Once the notice is served and the lien claim is recorded, a subcontractor can proceed to enforce its lien claim.

Section 5 Notice

Subcontractors who work on single family owner occupied residences have yet another notice to send out pursuant to Section 5 of the Illinois Mechanics Lien Act. Within 60 days of the subcontractor’s first date of furnishing, a subcontractor must send a notice to the property owner via certified mail, return receipt requested with a copy to the general contractor which contains: